Generic Risk Assessment - Photo Finish

Photo Finish Equipments - Photographic (Wet) and Video Camera Installations

 

 

HazardWho/How AffectedControl Measures
Temporary/ Permanent Out-field/In-field Scaffold Tower Wet/Video Camera Location. Technical Officials, Athletes: - Injury from falling and collision.

1. In the case of temporary scaffolding towers, ensure that the tower in constructed to the manufacturers specifications and correctly tagged. For permanent towers/fixtures ensure safety information plate is in place, legible and in date. 

 

2. Ensure that the working platform flooring is securely attached to the tower framework. 

 

3. Ensure that the working platform safety rail is at the regulation height above the level of the platform floor, not-with-standing the camera's line of view. 

 

4. Ensure that the tower is securely braced and stabilized against the ground environment.

 

5. Ensure that access to the working platform is preferably from within the ground foot-print of the scaffold tower. 

 

6. Ensure that the working platform access device is safe and secured to both the working platform and ground environment. 

 

7. Ensure that high visibility tape is wound around the lower tower extremities from ground level to a height of 2 metres.

 

Control measure responsibilities: 1. Facility staff. 2. Facility staff, Technical Officials, PF Equipment Provider(if appropriate) 3. Facility staff, Technical Officials, PF Equipment Provider(if appropriate) 4. Facility staff, Technical Officials, PF Equipment Provider(if appropriate) 5. Facility staff, Technical Officials, PF Equipment Provider(if appropriate) 6. Facility staff, Technical Officials, PF Equipment Provider(if appropriate) 7. Facility staff, Technical Officials, PF Equipment Provider(if appropriate)

 

IF CONTROL MEASURES ARE IMPLEMENTED, THEN RISK IS LOW

 

Permanent Out-field Wet/Video Camera Location Technical Officials:- Injury from falling

1. Ensure that the aperture through which the PF camera points towards the track has a suitable safety rail(s) to prevent PF operatives from falling on to structures below the camera location.

 

2. Ensure that all PF technical officials are aware of the opening facility.

 

Control measure responsibilities: 1. Facility staff, PF Equipment Provider (if appropriate) 2. Technical Officials

 

IF CONTROL MEASURES ARE IMPLEMENTED, THEN RISK IS LOW

 

Temporary Single Pole In-field Video Camera Mounting. Athletes, Officials:-Injury from falling, collision

1. Ensure that the pole is securely fastened to its ground anchorage.

 

2. Ensure that the pole is of a contrasting colour to its surroundings.

 

3. Ensure that when accessing the camera, an 'A' frame ladder is used suitably braced and steadied by a competent person.

 

Control measure responsibilities: 1. Facility staff, PF Equipment Provider (if appropriate) 2. Facility staff, PF Equipment Provider (if appropriate) 3. PF Equipment Provider (if appropriate)

 

IF CONTROL MEASURES ARE IMPLEMENTED, THEN RISK IS LOW

 

Temporary Stand Alone Video Camera Mounting Tri-pod. Athletes, Officials:-Injury from falling, collision

1. Ensure that the tri-pod is securely positioned.

 

2. Ensure that the tri-pod is of a contrasting colour to its surroundings.

 

3. Ensure that when accessing the camera, an 'A' frame ladder is used suitably braced and steadied by a competent person.

 

Control measure responsibilities: 1.Technical Official, Athletes, PF Equipment Provider (if appropriate) 2.Technical Official, Athletes, PF Equipment Provider (if appropriate) 3. Technical Official, PF Equipment Provider (if appropriate)

 

IF CONTROL MEASURES ARE IMPLEMENTED, THEN RISK IS LOW

 

Wet Camera Installation. Technical Officials:-Injury from electric shock, tripping and falling

1. Ensure that all Mains power supply outlets have switches and power 'ON' indicators.

 

2. Ensure that all Mains power supply plugs and associated cables have in-date safety labels.

 

3. Ensure that all electrical cables are routed away from the operating area and protected on the floor by rubber cable mats.

 

Control measures responsibilities: 1. Facility staff. 2. PF Equipment Provider, Technical Officials. 3. Facility staff. PF Equipment Provider, Technical Officials.

 

IF CONTROL MEASURES ARE IMPLEMENTED, THEN RISK IS LOW

 

Video PF Equipment Installation. Technical Officials:-Injury from electric shock, tripping and falling.

1. Ensure that all Mains power supply outlets have switches and power 'ON' indicators.

 

2. Ensure that all Mains power supply plugs and associated cables have in-date safety labels.

 

3. Ensure that all electrical cables are routed away from the operating area and protected on the floor by rubber cable mats.

 

Control measures responsibilities: 1. Facility staff. 2. PF Equipment Provider, Technical Officials, Transducer Operator. 3. Facility staff. PF Equipment Provider, Technical Officials, Transducer Operator.

 

IF CONTROL MEASURES ARE IMPLEMENTED, THEN RISK IS LOW

 

Automatic Starting Device(s) Installation. Athletes/Technical Officials/General Public:-Injury from tripping and falling.

1. Ensure that all electrical cables are routed via dedicated cable ways, near to the inside of the inside track kerb and protected from athletes/general pedestrian traffic by rubber cable mats.

 

2. Ensure that where no special provision is made for the egress of cables from manholes, notices are displayed warning of raised manholes.

 

Control measures responsibilities: 1,2 Facility staff. PF equipment suppliers, Technical Officials.

 

IF CONTROL MEASURES ARE IMPLEMENTED, THEN RISK IS LOW

 

Photographic Chemicals Technical Officials:-Injury from spillage, splashing and inhalation of fumes .

1. Ensure that the preparation, mixing and pouring of individual photographic chemicals are carried out in a well ventilated area, to the chemical manufacturer's guidelines.

 

2. Ensure that dedicated equipment and utensils are used for each chemicals.

 

3. Ensure that protective glasses, gloves and overalls are used when preparing, mixing and pouring PF chemicals.

 

4. Ensure that caution is taken when PF film is taken:- a. From the development tank after the normal process of film processing. b. From both the individual developer and fixer tanks;- i. When dismantling and cleaning the PF camera at the end of an Meeting. ii. When changing films.

 

5. Ensure that an eye wash, copious amounts of cold water and washing facilities are located in the immediate vicinity of the PF camera and operatives.

 

6. Ensure that food and drink are not consumed in the vicinity of the PF camera.

 

Control measure responsibilities: 1. Technical Officials. 2. Facility staff, Technical Officials. 3. Facility staff, Technical Officials. 4. Technical Officials. 5. Facility staff. Technical Officials. 6. Technical Officials.

 

IF CONTROL MEASURES ARE IMPLEMENTED, THEN RISK IS LOW

 

Results Clips Technical Officials/Athletes/General Public:-Injury through collision with results clips

1. Ensure that the area below the PF operating position, in which a results clip is dropped, is cordoned and warning notices displayed.

 

2. Ensure that the area below the PF operating position is clear of all personal before a results clip is dropped.

 

Control measure responsibilities: 1. Facility staff, Technical Officials. 2. Technical Officials.

 

IF CONTROL MEASURES ARE IMPLEMENTED, THEN RISK IS LOW